What Wisconsin Requires in a Concrete Contract
Driveways, sidewalks and patios are named outright in the state's home improvement rule. What that means for the paperwork, the deposit, the permit and the ready-mix bill you never see.
Most homeowners buy concrete work perhaps twice in a lifetime, and the buying part is where things go wrong far more often than the pouring part. The good news is that Wisconsin has written down, in some detail, what a residential contractor owes you before, during and after the job. The rule is chapter ATCP 110 of the state's administrative code, and it is short enough to read in one sitting.
This page picks out the parts that matter on a flatwork job. It is a guide to what to look for, not legal advice. If you are gathering prices for a new drive, our concrete driveway page is where a visit is arranged, and the crew who comes will set their own contract terms within this rule.
Your job is squarely covered
Some consumer rules leave you guessing whether they apply. This one does not. The definition of a home improvement in ATCP 110.01 lists the construction, replacement and repair of driveways, sidewalks, patios and garages by name. A new drive, a replaced walk and a patio behind the house are all inside it.
When it has to be in writing
Under ATCP 110.05(1) a written contract is required in two situations, and at least one of them applies to nearly every concrete job:
- when you pay anything before the work is complete, which includes a deposit; or
- when the seller approached you, by knocking on the door, calling, mailing or leaving a leaflet.
Where a written contract is required, or you sign one anyway, it has to be signed by all parties and set out its material terms. The contents are specified.
| ATCP 110.05(2) item | What that looks like on a concrete job |
|---|---|
| Seller's name and address, and the salesperson's | Who you are actually contracting with |
| Description of work and principal materials | Area, thickness, base, reinforcement, finish |
| Total price, including finance charges | One number, or a stated labour rate if time and materials |
| Start and completion dates or period | A window, not "when we can fit you in" |
| Any warranty or guarantee | Stated in the document, not only spoken |
| Other documents forming part of it | The drawing, the permit, the spec sheet |
Two further rules sit beside that list. You must be given a copy before work starts or any payment is taken. And if the contract includes liquidated damages against you for breaking it, they cannot exceed ten percent of the price.
The deposit, and what it can be spent on
Paying something up front is ordinary in this trade, and the rule allows it. What it adds is a restriction: under ATCP 110.02(10), money paid before completion may only be used for materials or services for your job. It is not working capital for somebody else's driveway.
If the work then slips past an agreed deadline without the notice described below, or without you agreeing a new date, ATCP 110.07 lets you cancel in writing and demand back whatever has not been spent on your job. The seller then has fifteen calendar days to return it, and thirty to give you a written account of how your payments were used.
Delays and changes
Concrete is weather-dependent, and dates move. The rule accepts that but asks for honesty about it. ATCP 110.027 requires timely notice of any delay beyond a contract deadline, with reasons and proposed new dates, and a revised deadline only takes effect once you agree to it in writing. Delays caused by the buyer, by a destructive act of nature or by civil disorder are exempted.
Changes to the job itself work the same way. Under ATCP 110.023 a verbal change is allowed only if it adds no cost and does not reduce the value of what you are getting, and the seller has to record it and report it to you before final payment. Anything that adds to the bill is a written change.
Permits come first
ATCP 110.03 requires the seller to tell you, before you sign, which permits the job needs, and it forbids starting work until they have been issued. On a Burlington driveway that meets the street this is not a formality. Curb and gutter, sidewalk and driveway approach work all need a Department of Public Works permit, with a $30 administrative charge for surface work and a $200 deposit where the excavation goes under the pavement or reaches twelve inches or deeper. Our page on how the city handles the kerb explains the rest.
Where inspections are required, the same section says copies of the inspection certificates are due to you before final payment.
The bill you never see: lien rights
This is the part of the buying process most homeowners have never heard of, and on a concrete job it has a very specific face: the ready-mix truck.
Under Wisconsin's construction lien statute, a supplier who delivered materials to your property can, if it is not paid by your contractor and it serves written notice on you within sixty days of first delivering, claim a lien against the property. You paid your contractor in full; the plant that batched your concrete may still have a claim if your contractor did not pay it. Wis. Stat. 779.02(2) also requires a prime contractor who buys in from subcontractors or suppliers, which on a pour means essentially every one, to print a lien notice in the written contract.
ATCP 110.025 gives you the defence. Before you sign, the seller must hand you a separate written notice saying you may request lien waivers, and if you ask, the seller must provide written waivers from contractors, subcontractors and material suppliers for the value supplied, at each payment you make. On a concrete job, asking for the ready-mix supplier's waiver with the final payment is the single most useful request in this whole article.
Three things a seller may not do
- Ask for the final payment early. Requesting a completion slip or final payment before the work is finished is a prohibited practice under ATCP 110.02(6)(e).
- Claim insurance vaguely. A seller who says they are licensed, bonded or insured must give you a written statement of exactly what they hold, under ATCP 110.02(4)(d).
- Invent urgency. Falsely telling you the existing concrete is dangerous or in need of replacement to win the job is listed among the prohibited practices.
A short checklist for signing day
- A written, signed contract with the six items above, and your own copy.
- The lien waiver notice, as a separate sheet you keep.
- A list of permits, and confirmation they are issued before anyone breaks ground.
- A payment schedule tied to stages, with the last payment after completion.
- A plan to request waivers, including the concrete supplier's, as you pay.
None of this should make a good contractor uncomfortable; it is the paperwork honest firms produce anyway. When you are ready to line up a price on a new drive, ask through our concrete driveway form and keep this list beside the estimate.
Sources
- Wis. Admin. Code ch. ATCP 110, Home improvement practices - the definition naming driveways, sidewalks and patios; prohibited practices; written change rules; lien waiver notice; delay notice; permits and inspection certificates; written contract requirements and contents; the 10% liquidated damages cap; cancellation, 15-day refund and 30-day accounting. Read 24 September 2026.
- Wis. Stat. 779.02, Construction liens - the prime contractor's notice in the written contract and the 60-day notice a supplier must serve to keep lien rights. Read 24 September 2026.
- City of Burlington Code, Ch. 274, Streets and Sidewalks - the Department of Public Works permit for curb and gutter, sidewalk and driveway approach work. Read 24 September 2026.